Central to the construction efforts is the stamping pit—an area vital for mass production. Here, significant developments are noted, with a new concrete pour occurring in the western section. The placement of thermal blankets and heaters is crucial for curing the concrete, a sign of the technical complexity involved in ramping up production capabilities.

The stamping pit’s framework is under considerable development, with rebar structures being both constructed and placed within the stamping area. These structural elements will form crucial supports that allow for the high-volume stamping processes necessary in the production line of the Tesla Semi.

Exterior Work and Utility Connections