Power Routing and Trenching: To manage outdoor power effectively, a trench was dug to run electrical cable underground from the house to the new outdoor outlet. This involved measuring, digging, and protecting the wiring from environmental elements.
Dealing with Existing Structures: The builder faced challenges like drilling through large posts and avoiding existing wires, necessitating careful planning and adaptation. For example, when drilling through a 6-inch wooden post, limited access and tight space required creative routing of wires.