Part 6/10:
The storm revealed weaknesses in the current setup, prompting adjustments. Particularly, a section of the site that experienced water pooling indicated that additional gravel or reinforced barriers might be necessary. The builder considered building up the ground around the structure with more gravel and concrete walls to prevent flooding during future heavy rains.
He also inspected the French drain’s performance, noting that while it wasn't fully tested yet, the current flow suggested it was functioning better than before. Water that previously flooded certain areas was now directed away effectively, indicating progress in the drainage system.