Part 2/10:

The client initially requested a 12x50 bunker, but terrain challenges rendered that plan unfeasible. Atlas's team, led by construction expert Ron, devised a solution: splitting the bunker into two modular sections. This approach allowed each module to be transported separately, making installation viable in the rugged terrain.

Key Steps in Installation:

  • Modular Assembly: Ron engineered the bunker in two modules, which were welded together on-site, ensuring an airtight, watertight seal.

  • Terrain Adaptation: Adjustments, like cutting a large bunker in half, prevented issues related to terrain elevation and obstacles, such as leaning trees.