He also raises concerns about traffic disruption and emergency access, highlighting the broader impacts on everyday life and public safety. Wallace’s stance reflects a cautious approach to protests that could destabilize the city’s infrastructure and social harmony.

Energy Policy Challenges and Cost Overruns

The discussion then turns to energy infrastructure projects, focusing on a critical project in Victoria that has faced staggering cost blowouts. A report from the Australian Energy Market Operator revealed that the Victoria to New South Wales Interconnector West, a high-voltage power lines project, has ballooned from an initial estimate of around $3.7 billion to a potential $11.4 billion, with current costs at about $7.6 billion.